Generator selection tends to go wrong in a predictable way. The conversation starts with a power figure — usually the rating of the machine the site already has, or the nearest size up from the first quote — and everything else follows from there.
Duty rating, load profile, starting current, site conditions and the system the generator will eventually sit in get treated as details to settle later. Sometimes they are settled later. Often they are not settled at all, and the consequences appear years afterwards: a standby-rated set asked to carry prime duty, a machine that cannot start the site’s largest motor, or a unit that delivers two-thirds of its nameplate output on a hot day at altitude.
Selection is a sequence of questions, and the questions are worth asking in order. This article sets out that sequence — duty rating first, then load, then starting current, then site conditions, and finally the range and configuration that fit.
Match the Duty Rating to the Way the Site Actually Runs
The first question is not how many kilowatts the site needs. It is what the generator will be asked to do, because a set’s rating is defined by its duty, not by its size.
ISO 8528-1, the standard that governs reciprocating engine driven generating sets, sets out the categories:
Emergency standby power (ESP). The set supplies a variable load when the normal supply fails, or during testing. Total annual running time is limited to about 200 hours, and the 24-hour average output is not to exceed 70% of the ESP rating. It is a backup rating — the machine is designed to sit idle and start when it is needed.
Prime power (PRP). The set supplies a variable load for an unlimited number of hours per year, in place of or in addition to a purchased supply. It carries a 10% overload capability, with the same 24-hour average limit of 70% of the rating. This is the rating for a site that generates its own power as a normal mode of operation.
Continuous power (COP). The set supplies a constant load continuously, for unlimited hours, under agreed conditions and maintenance intervals. There is no overload capability specified. This is the rating for base-load duty, such as an isolated plant or a remote substation.
Limited-time power (LTP). Maximum power for a limited number of hours per year — commonly around 500 — with no overload capability. It suits peak shaving or short-term parallel operation with a utility supply.
The practical consequence is straightforward: a standby set and a prime set of the same nominal output are not interchangeable, and the difference is not marketing. Running a standby-rated machine as a continuous prime source means operating outside the duty it was designed and warranted for, and the maintenance interval and service life expectations that came with it no longer apply.
Size from the Load Schedule, Not from the Machine You Have
Once the duty is settled, sizing starts from a load schedule rather than from a power figure. The load schedule lists everything the generator may have to carry: motors and drives, process equipment, HVAC, lighting, UPS and rectifier loads, and the site’s auxiliary systems.
Apply diversity, but not everywhere. Not every connected load runs at once, and a diversity or demand factor reflects that. The exception matters more than the rule: the starting surge of the largest motor should not be reduced by a diversity factor, because when it starts, it starts at full inrush.
Check the ratio of generator capacity to running load. Rules of thumb differ by load type — roughly 1:1 to 1.1:1 for resistive loads, 1.5:1 to 3:1 for mixed loads with motors depending on the largest motor’s starting current, and higher still for precision loads such as data centre equipment. The ratio is not arbitrary: it is the margin that lets the set absorb a load step without the voltage collapsing.
Add a margin that matches the duty. Common practice is in the region of 10–20% for standby applications, 20–30% for prime or continuous duty, and 30–50% where high starting currents are involved. The margin covers load growth and the difference between a calculated figure and the way a site actually behaves.
Convert to kVA at the site’s power factor. Generator ratings are usually expressed in both kW and kVA, and the relationship depends on power factor — commonly taken as 0.8 for this class of load. A load schedule built in kW has to be converted before it is compared with a kVA rating, and the comparison has to be made in the right units.

Starting Current Is Usually the Constraint, Not Running Load
On most industrial and commercial sites, the total running load is not what decides the size of the set. The largest motor starting is.
The inrush current of an induction motor is a multiple of its full-load current, and the multiple depends on how it is started. Direct-on-line starting draws roughly six times full-load current. Star-delta starting reduces that to around three times. A soft starter brings it down to roughly one and a half times, and a variable speed drive changes the profile again. The generator has to absorb that surge while continuing to supply everything else that is already running.
Two limits define whether it can. The first is voltage dip: a transient dip within about 15% is generally tolerable for the rest of the site, while a dip beyond roughly 25% risks the generator stalling or tripping — and, on a site with sensitive equipment, risks the equipment dropping out first. The second is the alternator’s overload capability, which depends on its excitation system. A self-excited shunt alternator typically offers around 180% overload capability; a permanent magnet or AREP excitation system can offer around 300% for about ten seconds, which is why those systems are commonly specified where large motors have to start.
This is why a site’s largest motor often determines the frame size of the generator, and why mitigation measures — soft starting, a variable speed drive, or sequencing the loads so the largest motor never starts while everything else is at full load — can reduce the required machine more effectively than any other design decision.
Derate for Altitude, Temperature and Enclosure
Generator ratings are quoted at standard reference conditions: sea level, 25°C ambient, and a defined relative humidity. Above those conditions, the machine cannot deliver its nameplate output, and the difference is significant enough to change the size that has to be ordered.
Altitude. Naturally aspirated engines lose roughly 3–4% of output per 300 m above sea level, because there is less oxygen to burn. Turbocharged engines lose less — commonly around 1–2% per 300 m — because the turbocharger compensates for the reduced air density, up to its own limit.
Temperature. Ambient temperature affects both combustion and cooling. A commonly used figure is around 1% of capacity lost per degree above 30°C, though the exact curve is engine-specific and should be taken from the manufacturer’s data.
The two derates multiply rather than add. Usable output is the nameplate rating multiplied by the altitude factor and the temperature factor — with parasitic losses such as enclosure cooling fans deducted as well. A 500 kW machine installed at altitude in a hot climate can end up delivering a little over 400 kW, and a selection made from the nameplate figure alone will be undersized at exactly the moment the site needs the power.
The practical rule: derate first, then compare with the load schedule. Selecting a machine and then checking the derating curve afterwards reverses the sequence and usually leads to a frame size that is one step too small.
What the Power Range Tells You About the Application
Power ranges map onto applications, and the mapping is a useful first filter when the load schedule is not yet complete.

From around 22 kW to 600 kW, the applications are typically factories and industrial plants with defined backup requirements, construction sites, commercial buildings needing standby power for essential services, and remote power applications where a small isolated supply is the alternative to no supply at all. Sets in this range are commonly supplied in open-type configuration, in prime and standby ratings, with output options across the range rather than at a single fixed point.

From around 600 kW to 2000+ kW and above, the applications shift to larger industrial plants, mining operations, and sites where the generator is carrying a substantial share of the load rather than covering essential services during an outage. At this scale the configuration questions change: paralleling, load sharing between multiple sets, the switchgear and protection that go with it, and how the generator interacts with the rest of the plant’s electrical system.
YURI POWER supplies diesel generator sets across this range, from approximately 22 kW to 2000+ kW, in small, medium and large frames for prime and standby duty, in open-type configurations with flexible output options. Available certifications published for the range include CE, UKCA, RCM and ISO 8528.
Where the Generator Fits in the Hybrid System
A generator is increasingly one component of a system rather than the whole answer — which changes what “selecting a generator” means.
Where a site has solar and battery storage alongside its generators, the generator’s role shifts from primary supply to firm capacity: it covers what the renewable generation and storage cannot, and it does so at a load factor the engine can actually tolerate. This matters because diesel engines are not designed to run indefinitely at a small fraction of their rating, and a hybrid system that displaces the generator without managing its loading will deliver fuel savings and an engine overhaul in roughly the same timeframe. That mechanism is set out in what a diesel generator hybrid retrofit actually takes.
For sites that already have generators, the selection question becomes a retrofit question — what has to be added, and what control layer has to manage the three sources together. For new projects, it becomes a system design question: how much firm capacity the site genuinely needs, which is a different calculation from how much load it has, as we set out in how much diesel backup a hybrid microgrid needs. And because the economics of a diesel-only supply are driven by fuel delivery and maintenance as much as by equipment, the comparison should be made on delivered cost per kilowatt-hour — the calculation in the real cost of diesel-generated electricity.
What to Confirm Before Ordering
Six items decide whether a selection holds up once the machine is on site. Each of them is easier to confirm before the order than after it:
– Duty rating — standby, prime or continuous, and whether the running hours the site expects match the rating being quoted.
– Load schedule with diversity factors, in both kW and kVA, covering every load the set may carry simultaneously.
– The largest motor’s starting method and current, and whether the alternator’s overload capability covers it.
– Site conditions — altitude, ambient temperature and enclosure — converted into a derating figure before the rating is compared with the load.
– Configuration and interface — open type or enclosed, the switchgear and protection arrangements, and how the set connects to the site’s existing distribution.
– Whether the generator will operate alongside other sources — a second set, solar, storage or a hybrid control layer — because that changes the control and protection requirements rather than only the equipment list.
YURI POWER supplies diesel generator sets from approximately 22 kW to 2000+ kW for prime and standby duty, with switchgear and distribution for the connection side of the installation, and integrates them with generation, storage and control where the site requires a hybrid system — including the retrofit configuration set out at diesel generator hybrid retrofit.

FAQ
Q: We have a figure from a supplier and just want to compare prices. What should we check first?
A: Check the duty rating behind the figure before anything else. A standby-rated set and a prime-rated set of the same nominal output are not the same machine, and if your site intends to run the generator as a routine source of power rather than only during outages, you need the prime rating quoted. Comparing two prices for two different duty ratings is the most common way a generator purchase starts to go wrong.
Q: Our load is about 300 kW. Is a 300 kW generator the right choice?
A: Almost certainly not, for two reasons. The running load is not the whole load — you need diversity factors applied to it, plus margin for load growth and the way the site actually behaves. And the largest motor starting is usually the real constraint: a direct-on-line motor draws around six times its full-load current for the duration of the start, and the generator has to absorb that without the voltage dipping far enough to disturb the rest of the site. The 300 kW figure is the start of the calculation, not the answer to it.
Q: Does altitude or high ambient temperature really change the size we need?
A: Yes, and by more than most people expect. Ratings are quoted at sea level and 25°C, and output falls above those conditions — naturally aspirated engines lose roughly 3–4% per 300 m of altitude, and around 1% per degree above 30°C. The two derates multiply rather than add. A machine specified without derating is a machine that will not deliver its nameplate output on the hottest day of the year, which is often the day it is needed.
Q: Should we specify one large generator or two smaller ones?
A: Two sets give redundancy, better part-load efficiency and a lower starting load per machine, at the cost of more equipment, more switchgear and a control layer that has to manage load sharing. One large set is simpler and usually cheaper to install. The deciding factors are how critical continuous supply is, whether a single set would spend most of its life at low load, and whether the site’s load grows in steps that a second machine could cover later.
Q: What do you need from us to recommend a generator?
A: Your load schedule, including the largest motors and how they are started. The duty you expect — standby only, or routine generation. Site conditions: altitude, ambient temperature and whether the set will be enclosed. The connection arrangements, including any existing switchgear. And a view of whether the generator will work alongside solar, storage or a second set. With those, we can put a duty rating, a size and a configuration against your site rather than against a catalogue page.
YURI POWER Engineering Team · September 17, 2026