Why South Africa’s Battery Storage Tenders Specify Four Hours

Two numbers define South Africa’s first grid-scale battery procurement. The programme set out to buy up to 513 MW of battery storage, and it specified at least 2,052 MWh of energy capacity.

Divide one by the other and the answer is four hours, exactly. That is not a rounding artefact, and it is not a coincidence produced by whichever projects happened to bid. The tender documents ask for it directly: a facility must be capable of operating continuously at its contracted capacity for a minimum of four hours.

Most battery storage sold for commercial and industrial use is built around two. The gap between those two numbers is not a matter of scale. It is a difference in what the storage is being bought to do.

Aerial view of a grid-scale battery energy storage facility with rows of battery containers on concrete pads, beside a high-voltage substation with transformers and steel structures, with transmission towers leading away across semi-arid ground

The Numbers Behind the Tender

South Africa’s Battery Energy Storage Independent Power Procurement Programme – BESIPPPP – was launched in March 2023 under the country’s Integrated Resource Plan. Its first bid window was modest by the standards of the generation procurements running alongside it: up to 513 MW, or at least 2,052 MWh, of battery storage.

Two features separate it from a conventional generation tender.

It is site-specific. The programme named five substations and invited bids for those locations only, with a single preferred bidder to be appointed per site. Bidders did not propose where the storage should go; the grid’s requirements fixed that, and the tender was built around those fixed points.

It buys services rather than electricity alone. The facilities are contracted to provide capacity, energy and ancillary services to the national utility – three distinct products, not one.

The market’s response suggests it had been waiting for the opportunity. Seventeen bids arrived by the August 2023 deadline and were evaluated independently over the following two months. Four preferred bidders were announced on 30 November 2023, with a fifth added in April 2024 once value-for-money negotiations concluded.

What the Tender Actually Requires

The four-hour figure is not an inference drawn from the capacity totals. It appears in the procurement documents as an obligation.

The request for proposals requires the facility to be able to operate continuously at its contracted capacity for a minimum of four hours. Bidders confirmed the same assumption in their own submissions: a dispatching assumption of four hours of battery storage capacity in one licensing application, and a requirement to provide four hours of stored energy per cycle during demand peaks in the technical design report for a comparable facility.

The energy total follows from that requirement. Five hundred and thirteen megawatts of contracted capacity at four hours is 2,052 MWh, which is the number the programme published.

It is worth being precise about what the requirement does and does not do. It is a floor, not a target: nothing prevents a developer from building more energy capacity than the four-hour rating demands, and a facility with a longer duration would exceed the requirement rather than violate it. What the floor rules out is a project that can only hold its contracted output for ninety minutes and then has to stand down.

Why Grid Storage Is Sized Differently From Commercial Cabinets

A commercial and industrial battery is usually sold at roughly a two-hour ratio, and there is a straightforward reason for it. Its revenue comes from displacing electricity that would otherwise be bought at an expensive time – the battery charges when power is cheap, discharges when it is dear, and the length of the discharge is set by the length of the expensive period. Since most commercial tariff windows run two to four hours, the pairings in a standard commercial range cluster around two hours.

Grid storage is paid differently, and the difference explains the longer duration.

Capacity is payment for being available. A facility that can deliver its contracted output on demand provides a service whether or not it is ever called on, and capacity arrangements exist precisely to pay for that availability rather than for electrons delivered.

Energy is the shifting function – moving generation from when it is abundant to when it is needed. This is the part that resembles commercial storage, and the part where duration is measured in hours.

Ancillary services keep the system stable: frequency response, voltage support, reserve. These are measured in seconds and minutes, but they require the plant to be online and responsive when called.

A four-hour facility can serve all three functions. A two-hour battery optimised purely for arbitrage is weaker on the first and third, because how long it can sustain output determines how long it can hold a position when the system needs it to. Duration at grid scale is therefore not primarily an economic optimum – it is a capability that has to be present before the facility can be contracted for the services it is being bought to provide.

There is a second reason grid storage runs longer. A commercial battery is sized against one site’s load profile, and that profile is bounded by what the site consumes. A grid-scale battery is sized against a system-wide condition – the evening peak after solar output falls away, or the shortfall left by an outage at a large generating unit. Those conditions are both larger and longer-lasting than any single customer’s demand.

Four Hours Is Not a Universal Answer

Four hours is what this programme asked for. It is not what every storage tender asks for, and the variation is the most instructive part.

Project Power Energy Duration
South Africa – BESIPPPP Bid Window 1 513 MW 2,052 MWh 4.0 hours
Tunisia – Bazma solar-plus-storage tender 150 MW 540 MWh 3.6 hours
Eswatini – solar-plus-storage RFI 40 MW 200 MWh 5.0 hours
South Africa – gravity storage at a coal site 25 MW 100 MWh 4.0 hours
Commercial and industrial cabinets 50-125 kW 100-233 kWh about 2 hours

The durations are the ratios of the two published figures in each case, not separate disclosures. Each reflects a different job. The Tunisian tender is paired with a 300 MW solar plant in a market building out renewables against a growing evening peak, and its storage is sized to cover part of that window. The Eswatini facility, at five hours, is being scoped for a smaller system where the storage carries more of the daily cycle. The commercial cabinet at two hours is doing neither of those things – it is reducing a bill.

A line of high-voltage transmission lattice towers receding into the distance across semi-arid scrubland, with conductors and insulators clearly visible under a blue sky

The lesson is not that four is the correct number. It is that duration is an output of the requirement, never an input. The same arithmetic that produces two hours for a retail site and four for a national procurement produces something else again where the requirement is to carry a load all night – which is why a mining installation sized against a five-hour peak window ends up with a different number again, and why an off-grid industrial plant built to supply firm power around the clock lands somewhere far beyond both.

Why the Sites Are Specified, Not Chosen

The site-specific structure of the tender is easy to read past, but it carries much of the design logic.

Storage connected to a grid does two things simultaneously: it stores energy, and it changes the operating conditions of the network at the point where it connects. A battery at a substation with constrained capacity can defer or avoid the need for network reinforcement. A battery at the end of a long rural feeder can hold voltage up in ways that no amount of generation elsewhere can. A battery near a load centre can reduce the flows that the transmission system has to carry during peak hours.

None of those benefits are interchangeable. A battery in the wrong place delivers the energy-shifting value and none of the network value, which is why a programme buying network services specifies where the equipment must sit rather than leaving the location to the bidder.

The five sites in the first window sit in the Northern Cape and North West provinces – areas with strong solar resource, long transmission distances and, in the Department’s framing, constrained grid capacity. Locating storage there addresses two problems at once: it adds dispatchable capacity, and it relieves the network constraints that make connecting new generation difficult.

For the second window, the same logic produced eight substations across North West, Gauteng and Free State, with capacity spread evenly across them at 76 to 77 MW per site. When the location is the design variable, the capacities come out uniform.

What Landed, and What It Committed To

Five projects were appointed, ranging from 77 MW to 153 MW, each at a different substation and each built to the same four-hour requirement.

The first four, announced together, total 360 MW and 1,440 MWh – which works out to precisely four hours again, confirming that the duration requirement carried through into the design of every individual project rather than only the programme total.

The facilities sell under 15-year power purchase agreements with the national utility. Fifteen years is a long contract by commercial standards, and it is what makes the economics of a four-hour grid battery workable: the revenue is contracted for long enough to support the capital cost, and the risk of the asset being stranded by market changes sits largely with the buyer rather than the developer.

The economic development commitments attached to the awards are worth noting for a different reason. Job creation, local content spending and preferential procurement were not mandatory conditions of this bid window – the Department said so explicitly when announcing the results. The appointed bidders committed to them anyway: 992 job opportunities measured in job years across construction and operation, more than R3.2 billion in local content, and more than R4.4 billion in preferential procurement from black-owned enterprises, qualifying small enterprises and exempted micro enterprises over the life of the projects.

Whether comparable commitments would be offered in a programme where they were compulsory is a separate question. What the outcome shows is that in a competitive window – seventeen bids for five sites – developers treat economic development terms as part of the offer rather than as a cost to be minimised.

What This Means If You Are Buying Storage

The most common mistake this comparison invites is a commercial buyer concluding that they should be specifying four hours. They usually should not.

Match duration to the requirement, not to a benchmark. If your objective is to reduce a demand charge or shift consumption out of a two-hour peak window, a two-hour system is the correct answer and a four-hour one is capital that will sit idle. If your peak window runs five hours, or your site has to run through the night without a grid, then two hours is the wrong answer and the fact that commercial cabinets cluster there is no defence.

Ask what you are actually buying. A grid-scale facility is paid for capacity, energy and ancillary services. A commercial battery is paid for avoided cost. The second is a smaller, simpler proposition, and it does not need the capabilities the first one does.

Check the connection before the equipment. Grid connection approval requirements can shape what is buildable at a site before any sizing work begins, and they vary by network and by jurisdiction. In the South African programme, the connection point was specified by the buyer – a luxury a single commercial site does not have, and one more reason to confirm the connection position early.

Two outdoor commercial battery storage cabinets on concrete plinths beside a distribution board and transformer, in front of an industrial building with loading bays and rooftop cooling units, with a small solar array to one side

YURI POWER supplies battery energy storage systems and energy management systems for commercial, industrial and off-grid applications, with system configurations developed against a site’s load profile, tariff structure and connection conditions. Final capacity and technical specifications are confirmed against project documentation and local requirements.

FAQ

Q: Why do grid-scale battery tenders specify four hours?

A: Because duration determines which services the facility can sell. A grid battery contracted to provide capacity, energy and ancillary services has to be able to sustain its contracted output long enough to be useful for all three – and the four-hour requirement in South Africa’s programme is written into the tender documents as a minimum, not derived from the totals afterwards. Commercial storage, which is paid for avoided cost rather than for services, has no equivalent requirement and clusters around two hours for the simpler reason that peak tariff windows are two to four hours long.

Q: Is four hours the standard duration for grid storage worldwide?

A: No. It is common, particularly where the storage is intended to cover an evening peak after solar output falls away, but it is not universal. Tenders in the same region have specified ratios closer to 3.6 hours and 5 hours for different system conditions, and longer durations appear where the requirement is to carry load overnight. The four-hour figure reflects the specific service mix a particular programme was buying, not a technical standard.

Q: Does a longer duration always mean a better system?

A: No – it means a system capable of a different job, at a higher cost. Every additional hour of duration is additional battery capacity, and capacity that is never cycled does not earn anything. The relevant question is how long the condition the battery exists to cover actually lasts. A two-hour battery on a two-hour peak window is fully used; a four-hour battery on the same site is half idle.

Q: How does a developer decide what duration to offer?

A: In a tender, the duration is set by the buyer, and the developer’s decision is whether the project can be profitable at that duration and price. For a site-specific commercial or industrial installation, the process runs the other way: you establish the condition the storage has to cover – the length of the peak window, or the number of hours without generation – and that figure sets the duration. The equipment follows from the requirement.

Q: What is the difference between capacity, energy and ancillary services?

A: Capacity is payment for being available to deliver a contracted output, whether or not the facility is called on. Energy is payment for electricity actually delivered, which is where shifting generation from one period to another is rewarded. Ancillary services cover the functions that keep a grid stable – frequency response, voltage support and reserve – and are typically measured in seconds and minutes rather than hours. A battery can provide all three, which is why grid-scale storage is contracted differently from a commercial system that only reduces a bill.

Q: Should a commercial site ever specify more than two hours?

A: Yes, in three situations. When the site’s expensive tariff window runs longer than two hours – four, five or six hours is not unusual on industrial tariffs – a two-hour battery covers part of it and leaves the rest to be bought at the highest price of the day. When the site has no reliable grid, duration is set by how long the battery has to carry the load alone, which is measured in hours of darkness rather than hours of peak tariff. And when the storage is intended to provide backup power for critical loads, the duration is set by how long those loads must run through an outage.

Q: Why were the storage sites specified by the buyer rather than proposed by bidders?

A: Because a grid-connected battery does two jobs at once: it stores energy, and it changes the operating conditions of the network at the point where it connects. Relieving a constrained substation, supporting voltage at the end of a long feeder and reducing peak flows on a transmission corridor are location-specific benefits that cannot be delivered from a different site. Specifying the location lets the buyer procure the network benefit as well as the energy, which would not be possible if bidders chose the sites.

YURI POWER Engineering Team · September 28, 2026