Most retrofit projects that go wrong do not fail on equipment selection. They fail on something that was already on site and was never properly examined — a generator controller with no usable interface, a distribution board with no spare capacity, a cable route nobody walked, or a maintenance contract that prohibits the change.
A retrofit is a project built around existing assets, and those assets decide more about the outcome than the new equipment does. This article sets out what to check before the project starts, and what a retrofit quotation should cover so that the scope can be compared with another supplier’s.
Why the Survey Decides the Project
On a new-build site, the design starts from requirements and works forward. On a retrofit, it starts from what exists and works around it. The existing generator, the existing distribution, the existing protection settings and the existing contracts all impose constraints before a single new component is chosen.
That inverts the usual order of work. The survey has to happen before the design, not after the quotation. A supplier who quotes a retrofit without asking about the generator controller or the spare ways in the distribution board is quoting a generic package, and the difference will appear during commissioning rather than during the price comparison.
The technical reasons a retrofit is harder than a new build are covered separately in what it actually takes to add solar and storage to an existing genset. This article is about the checks that come before that.

What to Check on the Existing Generator
| What to check | Why it changes the project |
|---|---|
| Rating, age and actual running hours | Nameplate rating tells you what the machine can do; running hours tell you what condition it is in. A set near a major overhaul interval changes the economics of retrofitting around it |
| Controller make, model and firmware | Determines whether a supervisory controller can communicate with it, and whether a controller upgrade is feasible or requires replacement |
| Communication interface | Modbus, CAN, dry contacts or nothing at all. A machine with no usable interface limits what the dispatch logic can do |
| Standalone or paralleled | A single set and a multiple-set plant need different control architectures and different protection arrangements |
| Recent fault and shutdown history | Repeated trips, overheating or starting failures indicate a machine that may not tolerate a new operating pattern |
| Actual load factor history | Most sites overestimate how hard the generator has been working. Logged data usually shows long periods at low load |
| Maintenance contract and warranty | A contract can restrict who may modify the control system. Check it before the design, not after |
The single most useful document here is the generator’s own operating log. Where one does not exist, a few weeks of logging before the project starts is worth more than any datasheet.

What to Check in the Existing Electrical System
The electrical system decides where the new equipment connects and whether the existing installation can accept it. Three things matter most.
Spare capacity in the distribution board. A retrofit adds outgoing ways for the PV inverter and the battery converter, and often a new incoming section for the control interface. A board with no spare ways means new switchgear, which changes the scope substantially.
Protection settings and their documentation. Adding generation and storage changes fault levels and can change the direction of power flow at points in the existing system. Settings that were correct for a generator-only site are not automatically correct afterwards. If the original protection study does not exist, it has to be produced — and that is engineering work, not an equipment line item.
Earthing and metering. The earthing arrangement has to suit the new sources, and the metering has to show what the site needs to see — particularly where the battery is charged from the grid or where the site is billed on a tariff with time bands.
Walking the cable routes is part of this check, not a detail to be resolved later. A route that looks straightforward on a drawing often is not, and the difference between a short and a long cable run can be one of the larger variables in a retrofit budget.
What to Check on Site
The physical checks decide where equipment goes, and they are the most common cause of a scope change after the quotation.
Where the PV can go. Roof area, structural capacity, shading and access, in the same sequence as any rooftop project. On an industrial site, the roof is often in worse condition than the operator believes, and the fix belongs in the retrofit scope rather than in a separate project later.
Where the battery and conversion equipment can go. Floor space, access for delivery and lifting, ventilation, fire separation and the distance to the existing electrical room. A container or cabinet needs a route to its position, not just a position.
Noise. A generator enclosure that has been acceptable for years may become a constraint once the operating pattern changes and the machine runs at different hours. The same applies to the new equipment.
Operating constraints. Where the site cannot be shut down, or can only be shut down in a defined window, that window becomes a design input. It affects the sequence of work, the temporary supply arrangements and, sometimes, whether the project is practical at all.
What a Retrofit Quote Should Cover
Once the survey is done, the quotation has to be read the same way as any other scope of supply. The items below are the ones that most often sit in the gap between two quotes.
| Scope item | Ask whether it is included |
|---|---|
| Survey and assessment of existing plant | Whether the supplier has visited, or quoted from photographs and a description |
| Generator controller modification or interface | Which route is proposed, and what happens to the existing protection and start logic |
| Protection study and re-setting | Whether the fault level study and the revised settings are in scope, or assumed to be by others |
| Communication and protocol integration | Who is responsible for making the new equipment and the existing controller exchange data, and what happens when a device drops off the bus |
| Cable, containment and trenching | The item most often listed as “by others” without saying by whom |
| Shutdown window and temporary supply | Whether the plan for keeping the site supplied during the works is part of the proposal |
| Commissioning and load testing | Functional testing, transition testing and the evidence that will be handed over |
| Operator training and documentation | As-built drawings, settings records and a handover explanation for the people who will run the system |
A lower quote is not automatically a narrower scope, but the two questions — what is included, and what is excluded — have to be answered before prices are compared. The same principle applies to storage quotations, as set out in commercial BESS quote comparison.
Three Assumptions That Usually Turn Out Wrong
“The generator is fine, it runs every day.” Running every day is not evidence of health. A set that has spent years at low load may already carry the deposits and wear that the retrofit will accelerate. The operating log and a physical inspection answer this; the fact that it starts reliably does not. The mechanism is described in the same article on the real cost of diesel-generated electricity.
“We will just add solar first and storage later.” This is a reasonable sequence, but it has to be designed as a sequence. A solar-only first phase still needs the control layer to stop reverse power and to keep the generator above its minimum load. If that is left for phase two, phase one may run for a year in a configuration that is quietly damaging the machine.
“The existing protection will be fine.” It was correct for the system that existed when it was set. A hybrid system is a different system, and the settings have to be reviewed by someone who has the fault level study in front of them. This is engineering work that is easy to leave out of a quotation and expensive to discover at commissioning.
What to Prepare Before Requesting a Quote
A supplier can only quote what they can see. The list below is the information that makes a retrofit quotation specific rather than generic:
– Twelve months of consumption data, ideally interval readings
– Generator details: rating, age, controller make and model, communication interface, and whether it runs in parallel with other sets
– The existing single-line diagram, and the protection settings if they exist
– Maintenance and fuel records, and the terms of any maintenance contract
– Site photographs or a walk-through of the proposed PV area, the battery location and the cable routes
– The shutdown constraints: when the site can be taken offline, and for how long
With those, a supplier can say whether the existing plant helps the project or constrains it — which is the question that decides whether the retrofit is straightforward. Where the site is still at an earlier stage, a preliminary system assessment is the better starting point. The retrofit configuration itself, from diesel generator hybrid retrofit through to the energy management system that coordinates the sources, is described on the linked pages.
FAQ
Q: Do we need a full electrical study before we can get a retrofit quote?
A: For a preliminary view, no. Load data, generator details, a single-line diagram and site photographs are enough to establish the shape of the project. A protection study and fault level calculation become necessary before the design is finalised, because adding generation changes the conditions the existing settings were based on.
Q: Our generator is old. Should we retrofit it or replace it?
A: It depends on condition and on how oversized it is. A machine that is sound and reasonably matched to the site’s firm capacity requirement is usually worth keeping. A machine near a major overhaul, or one that is far larger than the site now needs, may be better replaced with a smaller set plus storage. The operating log and a physical inspection answer this more reliably than the age alone.
Q: Can we keep the existing generator controller?
A: Often yes, by adding a supervisory controller alongside it that commands the existing start and stop logic while directly controlling the new PV and battery equipment. Whether that is the right route depends on the controller’s interface and on whether the site needs islanded operation or precise load sharing, both of which usually call for a controller upgrade.
Q: How disruptive is the installation?
A: It depends mainly on the shutdown window and on the cable routes. Most of the new equipment can be installed while the site runs, with the disruptive work concentrated at the connection point and during commissioning. The plan for keeping the site supplied during that work belongs in the proposal rather than in the contractor’s schedule.
Q: What is the most common reason retrofits run over budget?
A: The existing installation turning out to be different from what the drawings or the operator described — a distribution board with no spare capacity, protection settings that were never documented, or a roof that needed work before it could carry an array. A survey before the quotation is what keeps those items inside the budget rather than outside it.